Commercial and public-sector flat roofing delivered across Scotland and the UK — with a focus on quality, safety and programme-driven delivery.

Education · Glasgow · 2026

St Roch's High School — Flat Roof Overlay

Flat roof overlay at St Roch's High School, completed in 3 weeks against a 6-week programme.

Outcome

Completed in 3 weeks against a 6-week programme.

Education · Glasgow · 2023–24

Shawlands Academy — Flat Roof Refurbishment & Roughcasting

Flat-roof refurbishment using a Bauder build-up, together with roughcasting works to the building.

Works included

  • Flat-roof refurbishment with a Bauder build-up
  • Roughcasting

GKR FS · Retail / Commercial · Edinburgh

Sports Direct, Princes Street — Flat Roof Strip & Cut-to-Falls Built-Up System

Full strip of the existing single-ply roof and replacement with a Bauder cut-to-falls insulated built-up felt system, carried out for GKR FS on Sports Direct, Princes Street, Edinburgh.

Works included

  • Full strip of existing single-ply roof covering
  • Bauder specification arranged for the project
  • Detailed pricing document prepared for the client
  • Cut-to-falls insulation
  • Built-up felt waterproofing system

Outcome

20-year product and workmanship guarantee

Completed Bauder flat roof on a two-storey school building in Leicester

GKR Group · Education · Leicester, England

Judgemeadow Community College — School Flat Roof Replacement

C&M Contracts Ltd were appointed by GKR Group to carry out a full flat roof replacement at a school in Leicester. We provided the initial survey and Bauder specified the system, presenting the client with three options. The existing roof was scraped back to the original asphalt deck and a two-layer overlay system was installed.

Works included

  • Initial roof survey and condition assessment
  • Bauder specification with three options provided to client
  • Full strip back to original asphalt deck
  • Installation of two-layer Bauder overlay system
  • All associated detailing and weatherproofing

Key challenges

  • Strict 6-week summer holiday deadline
  • Occupied school environment
  • Full strip back to original deck required
  • Programme-critical delivery

Our solution

Detailed pre-construction planning with Bauder specification. The project was carefully programmed to fit within the 6-week summer holiday window. Our experienced team managed the full strip back to the original asphalt deck and installation of the new two-layer overlay system efficiently, maintaining quality and safety throughout.

Outcome

Project completed in just 4 weeks — 2 weeks ahead of the 6-week deadline — with no issues. The client was issued with a 20-year product and workmanship guarantee. Excellent feedback from GKR Group and the school.

Judgemeadow Community College flat roof replacement — second view
Judgemeadow Community College flat roof replacement — third view

Education · Glasgow

John Paul Academy

Flat roofing works at John Paul Academy, Glasgow.

Education · Glasgow

Glasgow Schools Refurbishment Programmes

Flat roofing on Glasgow schools refurbishment programmes, working with major UK main contractors.

Commercial Roofing Refurbishment — aerial view of the completed roof

Main Contractor · Commercial / Public Sector · Scotland

Commercial Roofing Refurbishment

C&M Contracts Ltd were appointed to carry out roofing refurbishment works as part of a wider construction programme. The works were undertaken on a live site with ongoing operations.

Works included

  • Removal of existing roofing system
  • Installation of new flat roofing system
  • Associated detailing and weatherproofing
  • Coordination with other trades and site management

Key challenges

  • Live site environment
  • Programme constraints
  • Interface with other contractors
  • Strict health and safety requirements

Our solution

Detailed pre-construction planning and RAMS. Close coordination with the main contractor and site team. Sequenced works to maintain safety and access. Daily communication and progress reporting.

Outcome

Works delivered safely and on programme. High-quality installation meeting specification. Positive feedback from the main contractor. Successful handover with no outstanding defects.

School Flat Roof Replacement in Scotland — completed roof viewed from above

Local Authority · Education · Scotland

School Flat Roof Replacement

Full flat roof replacement at an operational school, requiring careful coordination with term times and school activities to minimise disruption to pupils and staff.

Works included

  • Strip and removal of existing flat roof
  • Installation of new Bauder roofing system
  • Renewal of rainwater goods
  • All associated flashings and detailing

Key challenges

  • Occupied school environment
  • Safeguarding requirements
  • Works during term time
  • Noise and access restrictions

Our solution

Phased programme aligned with school calendar. Enhanced safeguarding measures and DBS-checked operatives. Dedicated site supervisor for liaison. Restricted working hours to minimise disruption.

Outcome

Project completed on time during school holidays. Zero safeguarding incidents. 20-year guarantee on roofing system. Excellent feedback from school management.

Industrial Building Refurbishment — aerial view of the roofing works

Facilities Management Company · Industrial · Scotland

Industrial Building Refurbishment

Comprehensive roof refurbishment of a large industrial unit including asbestos removal and replacement with modern roofing system.

Works included

  • Safe and compliant asbestos removal
  • New insulated roofing system
  • Rooflights and ventilation
  • Gutter and downpipe replacement

Key challenges

  • Asbestos containing materials
  • Operational facility
  • Large roof area
  • Weather-dependent works

Our solution

Qualified asbestos removal by trained operatives. Sectional approach to maintain building use. Weather monitoring and contingency planning. Regular client updates and progress reporting.

Outcome

Safe removal of all asbestos materials. New roof system with improved thermal performance. Works completed within budget. Building remained operational throughout.

Our work

Project gallery

Commercial Flat Roof Installation
Commercial Flat Roof Installation
Asbestos garage roof removal — before and after
Asbestos garage roof removal — before and after
Asbestos garage roof before removal
Asbestos garage roof before removal
New flat roof installed after asbestos removal
New flat roof installed after asbestos removal